EPIC for Consolidated Pipeline/Piping Replacement Works (Combined Package A & Package B)

Afjat Muaither RPS and Associated Pipelines

Rehabilitation / Reconstruction of Selected Awka Roads

Expand Shaybah – Abqaiq Pipeline Capacity

Location: KSA – Riyadh area – East/West Corridor

Client: Saudi Aramco

Value: $75M – $250M

Timeline: 2014-2016. 2 years

Scope Included:

  • Engineering, procurement, and construction contract for 220Km of 42-inch oil pipeline with 2 launcher/receiver areas
  • 5 mainline valve stations
  • 6 surge relief skids
  • Leak detections system
  • Corrosion monitoring system
  • Cathodic protection system
  • Remote Terminal Units and 2 operation shelters

Unique Challenges:

  • Terrain – Work conducted in the remote desert area
  • Logistics – Considerable distance to supply construction and support materials

C.A.T. Business Goals:

  • Aim – Required to take on the project from a competitor who withdrew, due to the exacting nature of the project’s scope and tight deadline.
  • Response – Despite not lowest bidder, the project was completed on time achieving client goals and expectations

Local Resources: Saudization was met as per project requirement (18% of total project manpower)

Safety Matters: Project delivered without lost time injury

Client Satisfaction/Awards: Exceeded client satisfaction. Project completed on time 