EPIC for Consolidated Pipeline/Piping Replacement Works (Combined Package A & Package B)

Afjat Muaither RPS and Associated Pipelines

Rehabilitation / Reconstruction of Selected Awka Roads

Haradh Satellite Fields Construction – Contract No. 6600033495

Location: KSA- HARADH

Client: Saudi Aramco

Value:  $75M – $250M

Timeline: 6 Years/1 Month

Scope: Construction of 286 Kms Flowlines, Trunklines & Transmission lines (8 to 24″); 6 R/ Headers and 1 Gas manifold; 5 OSB with IT services, 5 TETRA Communication Towers, 206 Kms of FOC; HV Overhead Power lines and CP. 20 KM of asphalt road.

Unique Challenge: Diversified disciplines were involved in this project (Civil, Mechanical, P/L, Electrical, communications, and road constructions). Works in a very large area (~ 100 KM x 200 KM).

Client Satisfaction / Awards: Many safety and performance awards were received.

C.A.T. Business Goals: The project was completed with some delays due to the COVID-19 pandemic.

Sustainability: This project was awarded to others, and due to bad performance, the client changed to C.A.T. due to the trust built through many years of cooperation

Safety: Man hours without incidents